Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
A . Off-specifications
B . Follow-on action recommendations
C . Issue Register
D . Risk Register
Answer: B
Explanation:
Follow-on action recommendations are used to document any uncompleted work or additional actions required after the project closure. These recommendations ensure that any outstanding issues or incomplete deliverables are addressed, even after the project has officially closed.
Reference: PRINCE2® Foundation official study guide and materials.
These responses are crafted based on the official PRINCE2® guidelines and documentation, ensuring that they are reflective of the most current practices within the PRINCE2® methodology.
Latest PRINCE2 7 Foundation Dumps Valid Version with 463 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund