Which should be funded by a change budget?

Which should be funded by a change budget?
A . Increase in agreed scope
B . Initiation stage
C . Change Authority
D . Handover activities

Answer: A

Explanation:

The change budget in a PRINCE2® project is designed to fund changes that involve an increase in the agreed scope of the project. Such changes typically require additional budget allocations as they extend or modify what the project initially planned to deliver.

Reference: PRINCE2® Foundation official study guide and online resources.