Which setting should be verified to make sure blades automatically power up upon power restore?
A VRTX server is being set up for a new customer and configured with four blades. After a shutdown from a power outage, blades do NOT power up automatically upon power restore. Blades can be powered up either manually or via CMC.
Which setting should be verified to make sure blades automatically power up upon power restore?
A . Verify Power Control Operations in the CMC GUI under Chassis Power Control
B . Verify chassis status with command racadm autopowerup Cm
C . Verify Power Configuration in the Lifecycle Controller GUI iDRAC Settings
D . Verify AC Power Recovery settings in the BIOS for each blade
Answer: A
Latest DCPPE-200 Dumps Valid Version with 92 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments