Which setting do you make to achive this?
You want to set up a make-to-order planing scenario for finished material. The bil of material contains two components: one should be procured for each sales order individually, the other one shold be procured jointly for all independent requirements. Forcasting for the finished product is NOT possible .
Which setting do you make to achive this?
A . Choose planning strategy 50 (Planning whthout final assembly) and select corresponding Mixed MRP indicator
B. Choose planning strategy 20 (Make-to-order) and select corresponding Invidual/collective indicator
C. Choose planning strategy 20 (Make-to-order) and select corresponding Mixed MRP indicator
D. Choose planning strategy 50 (Planning whthout final assembly) and select corresponding Invidual/collective indicator
Answer: D