Which Scrum accountability (role = outdated term) is responsible to do all the work required to turn Product Backlog in potentially releasable items?

Which Scrum accountability (role = outdated term) is responsible to do all the work required to turn Product Backlog in potentially releasable items?
A . The Business Analyst.
B. The Project Manager.
C. The Development Team.
D. The Stakeholders.

Answer: C

Explanation:

There are no Project Managers ans Business Analysts in Scrum. Stakeholders only provide the requirements for the Product Backlog items but will not support the development (directly).