Which Scrum accountabilities (roles = outdated term) have to attend the Daily Scrum?
A . The Scrum Master.
B. The Project Manager.
C. The Developers.
D. The Product Owner.
E. The Business Analyst.
Answer: C
Explanation:
In the Daily Scrum only the Developers have to attend (participate), but anyone can attend (watch, not talk/participate). There are no Business Analysts and Project Managers in Scrum.