Which scheduling strategy do you select?

You want to schedule an operation finitely, without removing other operations.

Which scheduling strategy do you select?
A . Insert operation
B . Squeeze in
C . Schedule in working time only
D . Find Slot

Answer: D

Explanation:

The Find Slot scheduling strategy allows you to schedule an operation finitely, without removing other operations. It searches for a free slot in the resource’s capacity that can accommodate the operation’s duration and constraints. If no suitable slot is found, the operation is scheduled at the end of the resource’s capacity. This strategy is useful for inserting urgent orders or operations into an existing schedule without disrupting it too much12

Reference: SAP S/4HANA Manufacturing for planning and scheduling – SAP Community SAP S/4HANA Manufacturing for Planning & Scheduling – Implementation Guide