Which risk response type (A-F) are they?
DRAG DROP
The project is in stage 2. The project manager has heard that a competitor may launch a similar e-learning course much sooner than ABC Company. There is a threat that the earlier launch of a competitor’s course may reduce the profitability of ABC Company training courses. Here are three responses to this risk.
Which risk response type (A-F) are they? Choose only one response type for each risk response. Each response type can be used once, more than once, or not at all.