Which response pays a third party to accept a risk?
A . Transfer
B . Prepare contingent plans
C . Accept
D . Avoid
Answer: A
Explanation:
Reference: https://twproject.com/blog/risk-response-strategies-mitigation-transfer-avoidance-acceptance/