Which process should the project manager have following before including the additional product feature?

A demanding project stakeholder insists that an additional feature be added to a project product without changing the scope, budget or schedule. The project manager allows this feature to be included since it adds great value to the end product. However, this lengthens the project schedule and increases project cost.

Which process should the project manager have following before including the additional product feature?
A . Change management
B . Schedule and cost management
C . Product scoping
D . Requirements definition

Answer: A