Which process numerically analyzes the effect of identified risks on overall project objectives?
Which process numerically analyzes the effect of identified risks on overall project objectives?
A . Plan Risk Management
B . Plan Risk Responses
C . Perform Quantitative Risk Analysis
D . Perform Qualitative Risk Analysis
Answer: C