Which process is triggered towards the end of the final stage when all the assigned work has been completed?
A . Managing a Stage Boundary
B . Managing Product Delivery
C . Closing a Project
D . Controlling a Stage
Answer: C
Explanation:
The Closing a Project process in PRINCE2 is triggered towards the end of the final stage when all assigned work has been completed. This process is designed to ensure that all project objectives have been achieved, all products have been delivered, and the project can be formally closed and evaluated for success and areas of improvement.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources