Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?

Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?
A . Estimate Costs
B. Control Costs
C. Determine Budget
D. Plan Cost Management

Answer: B

Latest CAPM Dumps Valid Version with 1089 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments