Which process involves determining, documenting, and managing stakeholders’ needs and requirements to meet project objectives?

Which process involves determining, documenting, and managing stakeholders’ needs and requirements to meet project objectives?
A . Collect Requirements
B . Plan Scope Management
C . Define Scope
D . Define Activities

Answer: A