Which process governs the project manager’s implementation of the approved change?

A project sponsor decides to add a feature to the project that affects the project cost, schedule, and scope.

The change is approved by the change control board.

Which process governs the project manager’s implementation of the approved change?
A . Monitor Risks
B . Control Cost and Schedule
C . Direct and Manage Project Work
D . Perform Integrated Change Control

Answer: C