Which process diagram fragment depicts correctly that a reminder is sent if Task A is not completed within 1 hour, without aborting the Task?

Which process diagram fragment depicts correctly that a reminder is sent if Task A is not completed within 1 hour, without aborting the Task?

A)

B)

C)

D)

A . Option A
B . Option B
C . Option C
D . Option D

Answer: C