HOTSPOT
You are a project manager using Dynamics 365 for Finance and Operations Lifecycle Services (LCS).
You must be able to identify and publish gaps within your normal delivery schedule.
You need to determine whether your organization has the minimum requirements in place to use Business Process Modeler (BPM).
Which prerequisites are required to use Business Process Modeler? To answer, select the appropriate options in the answer area. NOTE: Each correct selection is worth one point.
Answer:
Explanation:
References: https://docs.microsoft.com/en-us/dynamics365/unified-operations/dev-itpro/lifecycle-services/bpm-overview
Latest MB-300 Dumps Valid Version with 242 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund