Exam4Training

Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?

You want to trigger in-house production of a semi-finished material before a sales order for the corresponding finished good is received.

Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?
A . Planning with final assembly (40)
B . Production by lot size (30)
C . Planning at assembly level (70)
D . Make-to-order production (20)

Answer: B

Exit mobile version