Exam4Training

Which plan provides the Business Case with costs during the Initiating a Project process?

Which plan provides the Business Case with costs during the Initiating a Project process?
A . Initiation Stage Plan
B . Project Plan
C . Stage Plan
D . Team Plan

Answer: B

Explanation:

During the Initiating a Project process in PRINCE2, the Project Plan provides the Business Case with necessary details, including cost estimates. This plan outlines the overall scope and timing of the project and sets the baseline for project management activities, including cost control.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

Exit mobile version