Which phase of the project life cycle develops a consumable solution in a collaborative and incremental manner?
A . Inception
B. Execution
C. Construction
D. Transition
Answer: C
Explanation:
Sufficient Functionality. While it is worthwhile pursuing a goal of a consumable solution (what Scrum calls a potentially shippable increment) at the end of each iteration, it is more common to require a number of iterations of Construction before the team has implemented enough functionality to deploy.. (Choose Your WoW, Different Life Cycles With Common Milestones, page 102).