Which phase of the project life cycle develops a consumable solution in a collaborative and incremental manner?

Which phase of the project life cycle develops a consumable solution in a collaborative and incremental manner?
A . Execution
B . Construction
C . Inception
D . Transition

Answer: B

Explanation:

In Disciplined Agile, the Construction phase of the project life cycle is responsible for developing a consumable solution in a collaborative and incremental manner. During this phase, the team iteratively builds the solution, working closely with stakeholders to ensure that the product or service being developed meets their needs and expectations. The Construction phase emphasizes agility, collaboration, and incremental development, where the solution evolves through repeated iterations, incorporating feedback and improvements at each step. This approach helps to minimize risks, adapt to changes, and deliver value more frequently.

Reference: PMI, "Choose Your WoW! A Disciplined Agile Delivery Handbook for Optimizing Your Way of Working (WoW)," which describes the Construction phase as the iterative process where the solution is developed incrementally and collaboratively.

PMI Disciplined Agile (DA) Toolkit, which outlines the phases of the DA life cycle, including the collaborative nature of the Construction phase.