Which phase in PDCA cycle assesses the effectiveness of the BCMS against requirements of the business continuity policy?
Which phase in PDCA cycle assesses the effectiveness of the BCMS against requirements of the business continuity policy?
A . Plan
B . Do
C . Check
D . Act
Answer: C