Exam4Training

Which phase does each objective match?

Consider the following ADM phases objectives.

Which phase does each objective match?
A . 1F-2G-3F-4F
B . 1E-2F-3E-4G
C . 1G-2E-3F-4E
D . 1F-2F-3E-4G

Answer: B

Explanation:

1E: To identify delivery vehicles (projects programs portfolios) that will deliver the Target Architecture 2F: To confirm readiness and ability to undergo change 3E: To determine whether an incremental approach is required and if so identify Transition Architectures that will deliver continuous business value 4G: To perform appropriate governance functions while the solution is being implemented

Reference: The TOGAF® Standard | The Open Group Website, Section 3.2 ADM Phases.

Exit mobile version