Which phase determines potential issues pertaining to the management of the BCMS?
A . Plan
B . Do
C . Check
D . Act
Answer: D
Latest ISO-22301 Lead Auditor Dumps Valid Version with 100 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund