Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?

Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?
A . The Sprint Goal
B . Sprint Review minutes.
C . The Sprint Backlog.
D . The release plan.

Answer: A