Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?
A . The Sprint Backlog.
B . The Sprint Goal
C . The release plan.
D . Sprint Review minutes.
Answer: B
Explanation:
The correct answer is B, because the Scrum Guide states that “the Sprint Goal is an objective set for the Sprint that can be met through the implementation of Product Backlog. It provides guidance to the Development Team on why it is building the Increment.” Therefore, the Sprint Goal provides the Development Team with a target and overarching direction for the Sprint.
Latest PSM I Dumps Valid Version with 197 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund