Which one of the following statements is true?

Which one of the following statements is true?
A . Independent reviews and quality audits form part of quality assurance to ensure the project manager delivers on time and to budget.
B . Quality assurance provides confidence to stakeholders that requirements for quality will be exceeded.
C . Quality control verifies that the project deliverables conform to specification, are fit for purpose and meet stakeholder expectations.
D . Quality planning enables the project manager to manage the trade-off between customer expectations and budget.

Answer: C