Which one of the following statements is most true about changing requirements in a change-driven approach to business analysis and requirements management?

Which one of the following statements is most true about changing requirements in a change-driven approach to business analysis and requirements management?
A . Change-driven approaches must use a change control system with a change control board.
B . Change-driven approaches only use a change control system for approved changes.
C . Change-driven approaches don’t use a formal change control process.
D . Change-driven approaches are driven by change control processes.

Answer: C

Explanation:

Change-driven approaches typically do not use a formal change control process, as requirements are prioritized and selected for implementation at the beginning of each iteration and no changes to the requirements occur during the iteration process.

Answer. A is incorrect. Change-driven approaches don’t typically use a change control board.

Answer. B is incorrect. This isn’t a valid statement to describe the processes of change within a change-driven approach to requirements management.

Answer. D is incorrect. This isn’t a valid statement to describe the processes of change within a change-driven approach to requirements management.