Which one of the following options is NOT valid to determine the task id for a task?
A . One can determine the task id as a part of the URL while reviewing a task in activiti-app.
B . One can determine the task id via the Tasks tab in activiti-admin.
C . One can determine the task id by checking the details of the related process using the Alfresco Process Services REST AP
E . One can determine the task id by reviewing the Monitoring tab in activiti-admin.
Answer: A
Explanation:
Reference: https://docs.alfresco.com/activiti/docs/admin-guide/1.5.0/#_using_activiti_administrator