Which one of the following is NOT a type of identified dependencies in a Scrum project?
Which one of the following is NOT a type of identified dependencies in a Scrum project?
A . Critical
B . Mandatory
C . Discretionary
D . Internal
Answer: A
Explanation:
Reference: http://blog.scrumstudy.com/dependency-determination-in-scrum-project/
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments