Which one of the following is NOT a type of identified dependencies in a Scrum project?

Which one of the following is NOT a type of identified dependencies in a Scrum project?
A . Critical
B . Mandatory
C . Discretionary
D . Internal

Answer: A

Explanation:

Reference: http://blog.scrumstudy.com/dependency-determination-in-scrum-project/