Which one of the following is a valid project Key Performance Indicator (KPI)?

Which one of the following is a valid project Key Performance Indicator (KPI)?
A . Staff appraisals.
B . Management buy in.
C . Milestone achievement.
D . Master schedule.

Answer: C