Which one of the following estimation approaches is appropriate at this stage of the project?

Topic 17, Scenario 10, V2 "Online Application"

While waiting for the responses, the test manager has been asked to prepare test plans to validate the software application delivered by the successful bidder.

Which one of the following estimation approaches is appropriate at this stage of the project? 2 credits
A . Create an estimate based on the function point analysis technique and test point analysis
B . Create an estimate based on the complexity of the code
C . Create an estimate based on the credentials of the successful bidder
D . Create an estimate based on a percentage of the development effort

Answer: A