Exam4Training

Which one of the following estimation approaches is appropriate at this stage of the project? 2 credits

Which one of the following estimation approaches is appropriate at this stage of the project? 2 credits
A . Create an estimate based on the function point analysis technique and test point analysis
B . Create an estimate based on the complexity of the code
C . Create an estimate based on the credentials of the successful bidder
D . Create an estimate based on a percentage of the development effort

Answer: A