Which one of the following best describes a project issue?
Which one of the following best describes a project issue?
A . A major problem that requires formal escalation.
B . A problem that the project manager has to deal with on a day-to-day basis.
C . An uncertain event that may or may not occur.
D . An opportunity that occurs through change control.
Answer: A