Which of these may a Development Team deliver at the end of a Sprint?
Which of these may a Development Team deliver at the end of a Sprint?
A . Failing unit tests, to identify acceptance tests for the next Sprint.
B . An increment of software with minor known bugs in it.
C . An increment of working software that is “done”.
D . A single document, if that is what the Scrum Master asked for.
Answer: C
Explanation:
The correct answer is C, because a Development Team should deliver an increment of working software that is “done” by the end of a Sprint. The Scrum Guide states that “the Increment is the sum of all the Product Backlog items completed during a Sprint and the value of the increments of all previous Sprints. At the end of a Sprint, the new Increment must be ‘Done,’ which means it must be in useable condition and meet the Scrum Team’s definition of ‘Done’.”