Which of these are Scrum Artifacts and which one posses commitment? (choose the 3 answers)
A . For the Increment, its commitment is the Definition of Done.
B. For the Sprint, its commitment is the Scrum Values.
C. For the Sprint Goal, its commitment is the Definition of Done
D. For the Sprint Backlog, its commitment is the Sprint Goal.
E. For the Product Backlog, its commitment is the Product Goal.
Answer: A,D,E
Explanation:
Scrum Guide:
Each artifact contains a commitment to ensure it provides information that enhances transparency and focus against which progress can be measured:
For the Product Backlog it is the Product Goal.
For the Sprint Backlog it is the Sprint Goal.
For the Increment it is the Definition of Done.
These commitments exist to reinforce empiricism and the Scrum values for the Scrum Team and their stakeholders.
Latest PSM III Dumps Valid Version with 62 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund