Which of the renewing were used to accomplish this?

A project team completes the identification of project and product requirements.

Which of the renewing were used to accomplish this?
A . Benchmarking, network diagram, and trend analysis
B . Work breakdown structure (WBS), trend analysis, and observation/conversation
C . Affinity diagrams, benchmarking, and observation/conversation
D . Brainstorming, affinity diagrams, and mind mapping

Answer: D