Which of the measures listed below would be the best measure to take in order to increase the motivation of the team?

Topic 9, Scenario 6, V2 "Independent Test Team"

The project has been running for a few months and the team seems not to be progressing in their test approach. The team also lacks drive and enthusiasm and is sometimes seen to be performing their tasks too slowly. You have been asked to recruit an extra person into the team.

In addition to introducing the new team member, you have decided to raise motivation .

Which of the measures listed below would be the best measure to take in order to increase the motivation of the team? 2 credits
A . Provide more time for testing in the schedule
B . Allow people to take some time off
C . Introduce entry criteria to the testing phase
D . Organize a meeting with senior management in which they address the importance of good testing for this project

Answer: D