Which of the following would the project manager MOST likely do?
A project team member highlights to the project manager that expensive licensing for critical software in use across the project may expire before the completion project.
Which of the following would the project manager MOST likely do?
A . Place a risk on the risk register and arrange a risk review with the appropriate stakeholders to accept and/or mitigate the risk.
B . Raise a purchase order to purchase the licensing and ask the team member to install it.
C . Amend the project scope and raise a project change request to obtain approval of the amendment.
D . Amend the project schedule and work breakdown structures to remove the use of the software from the project.
Answer: A
Latest PK0-004 Dumps Valid Version with 574 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments