Which of the following would NOT be discussed at the Sprint Retrospective? (Choose two answers)
Which of the following would NOT be discussed at the Sprint Retrospective? (Choose two answers)
A . Team interactions.
B . The Definition of Done.
C . Improvements to the working process.
D . Sprint Backlog for the upcoming Sprint.
E . The features delivered in the Sprint.
Answer: D, E