During a remodel of an auditorium a second projector was added. The first protector was rotated so the image is duplicated on another section of the front wall Both projectors are connected to the switch through a VGA splitter After the move users report the images on the second projector are normal but images on the first projector are skewed.
Which of the following would correct the issue?
A . Replace the lamp on the projector
B . Adjust the projector’s keystone
C . Change the projector’s resolution
D . Power cycle the projector
Answer: B
Latest 220-1001 Dumps Valid Version with 718 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund