Exam4Training

Which of the following would BEST be managed with the keep satisfied" stakeholder management strategy?"

Which of the following would BEST be managed with the keep satisfied" stakeholder management strategy?"
A . Those with high power/influence and no interest in the project.
B. Those with high power/influence and some interest in the project.
C. Those with some power/influence and high interest in the project.
D. Those with some power/influence and some interest in the project.

Answer: B

Exit mobile version