Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?
A. Memorandum of understanding
A. Request for information
B. Statement of work
D. Non-disclosure agreement
Answer: B
Explanation:
The statement of work (SOW) would be the next document that a project manager should update once the need to procure goods and/or services is identified. A SOW is a document that defines the scope, deliverables, schedule, and terms and conditions of a project or contract. A SOW typically includes information such as purpose, scope of work, location of work, period of performance, deliverables schedule, applicable standards, acceptance criteria, special requirements, and payment schedule. A SOW can help to establish a common understanding and agreement between the client and the service provider on what needs to be done and how it will be done.