Which of the following would be the MOST useful option?
For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities.
Which of the following would be the MOST useful option?
A . Resource plan
B . Organizational chart
C . Project charter
D . RACI chart
Answer: D
Explanation:
A RACI chart would be the most useful option for the project manager to illustrate roles for major project activities for an upcoming project kickoff. A RACI chart is a visual representation of a RACI matrix that shows who is responsible, accountable, consulted, and informed for each task or activity in a project using a table format. A RACI chart can help to communicate and document the roles and expectations of each team member and stakeholder for the project and ensure alignment and agreement.