Which of the following would be the most significant input to estimating the time to carry out the specified testing tasks? 3 credits

Which of the following would be the most significant input to estimating the time to carry out the specified testing tasks? 3 credits
A . The skills and experience of developers to correct the failures.
B . The standards used for the requirements specification.
C . The metrics recorded from testing the capture-replay tool.
D . The number of testers in the company and their grade.

Answer: C