Which of the following would be the most important selection criterion for defining the priority of the recommendations?
A test assessment has been carried out using the selected model as a reference framework. A number of recommendations have been identified and you are asked to prioritize them. Based on your knowledge of the project, you are expecting severe resistance to change.
Which of the following would be the most important selection criterion for defining the priority of the recommendations? 2 credits
A . Synchronized with the overall long-term organizational strategy
B . Defined according to the maturity model used
C . Most visible to stakeholders
D . Low costs actions first
Answer: C