Which of the following would be the MOST appropriate action for the project manager with respect to the change request?
An IS auditor is involved with a project and finds an IT project stakeholder wants to make a change that could affect both the project scope and schedule.
Which of the following would be the MOST appropriate action for the project manager with respect to the change request?
A . Recommend to the project sponsor whether to approve the change
B . Modify the project plan as a result of the change
C . Evaluate the impact of the change
D . Ignore out-of-scope requests
Answer: C