Your department has several teams working on different products at the same time.
Which of the following would be the best approach if managers want to understand the status of each team? (choose the best answer)
A . Ask the teams to collaborate and develop a common way to share their goals and achievements toward their goals for each planning period.
B. Have a common status reporting tool that each team will fill out and can be shared with the managers.
C. Have the teams created a comprehensive project plan and track their work against the plan.
D. Have the teams standardize their estimation practices across all teams to make it easier to compare
the performance of each team.
Answer: A
Explanation:
Agile teams are structured and empowered by the organization to organize and manage their own work. The teams are responsible for applying the most appropriate practices to provide transparency in order to optimize value and control risk.