Which of the following would allow the business analyst to determine the impact for the specific requirement change?

During the project execution phase, the client requests the addition of a new feature.

Which of the following would allow the business analyst to determine the impact for the specific requirement change?
A . Requirements baseline
B . Requirements management tool
C . Requirements cards
D . Requirements traceability matrix

Answer: D